Project Schedule/ Status according to Matt:

Day 1: PLanned-Site survey Actual- Site Survey

Day 2: Planned-Rebar 1 Actual-Rebar 1….. First contact with the monkeys. Max wounded

Day 3: PLanned- Rebar 1 Actual- Rebar 1

Day 4: Planned- Formwork lift 1 Actual- Formwork lift 1….. Fended off first monkey invasion

Day 5: PLanned-Formwork lift 1 Actual- Formwork lift 1…. Max recoveres, 2nd monkey attack

Day 6: Planned-Pour Day Actual- Pour Day!… Truce Negotiated with the monkeys

Day 7: Planned- Rebar 2 Actual- Rebar 2

Day 8: Planned-Strip and place forms Actual- Strip and Place Forms 2

Day 9: Planned-Pour Day Actual- Strip and Place Forms 2…… small zombie outbreak

Day 10: Planned- Rest Day Actual- Pour Day

Day 11: Planned- Rebar 3 Actual- Rest Day….. Zombie Outbreak quelled.Trip to Mussoourie

Day 12: Strip and place forms

Day 13: Pour Day

Day 14: Rebar 4

Day 15: Strip and place forms

Day 16: Pour Day

Day 17: Rest

Day 18: Disassemble forms

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s